Rebuild Outlines

From DBArtisan
Jump to: navigation, search

Go Up to Available object actions by DBMS

You can rebuild one or more stored outlines in a single operation.

Platform Availability

To Rebuild a Stored Outline

  1. Initiate a Rebuild Outlines action against one or more stored outlines. For more information see Initiating an object operation.
  2. Use the following table as a guide to understanding and modifying settings in the Rebuild Outlines dialog:
Step Settings and tasks

Action options

Displays the stored outlines you selected.

Dependencies

Lets you review the objects potentially impacted by this action.

Preview

Preview the DDL generated for the operation. For more information, see Preview.

3. Click Execute. For information on the scheduling option, see Scheduling.